Development Update - Sep 2014
  • There was plenty of activity to keep the Bloomdale team warm this winter, thanks to the sale of more than 130 lots, the completion of the first four stages and the community park that is set to flourish this Spring.
  • The new community park provides residents with an in-built table tennis table, large playground, BBQ facilities, benches, walking paths, bike tracks and landscaped surrounds to enjoy with your family; a central hub for the Bloomdale community to gather.
  • Civil works for the Teatree Release have already commenced and include the completion of the drainage reserve and associated landscaping. Titles are expected in November 2014.
  • Works to upgrade Plumpton Road are progressing well and on track for a November completion, subject to weather.
  • Civil works for our next 35 lot Mountview Release are expected to commence in October 2014 with titles in April 2015.